When should you reorder? A buyer’s guide to Odoo 20

You have 100 units on the shelf, but a customer is collecting 80 tomorrow. Will the remainder last until the next delivery? That question is more useful to a buyer than today’s stock count. Recent ERP releases bring the information needed to answer it closer to the purchasing decision.

What changed in Odoo and the wider ERP market?

In September 2026, Odoo announced that version 20 can calculate minimum and maximum stock levels using the last 30 days of sales and prepare a draft purchase order. Reordering rules already existed. Buyers now have a starting point drawn from their own sales when they review those thresholds.

On 17 November at Ignite, Microsoft outlined how Dynamics 365 brings business data into Copilot and familiar tools such as Teams and Excel. Both announcements bring recommendations closer to where people act on them. For a buyer, the deciding question remains whether recent sales reflect what customers will need during the next lead time.

Start with one item in one warehouse

Suppose your Riyadh warehouse sells 12 units a day. Your supplier takes five days to deliver, and you want two days of safety stock. Here is a manual estimate you can use to sense-check the item’s settings.

MeasureCalculationResult
Lead-time demand12 × 560 units
Safety stock12 × 224 units
Suggested reorder point60 + 2484 units

How much should you buy?

Assume forecast stock on the planning date is 70 units, including confirmed receipts and issues, and your target maximum is 144. The forecast is below 84. Reaching the target would take 74 units. If you buy in multiples of 12, the order rounds up to seven cases, or 84 units. The resulting forecast is 154. The pack size explains the overshoot. All figures are illustrative.

When should a buyer adjust the suggestion?

Ahead of Ramadan, check confirmed customer orders and scheduled promotions. If the item was unavailable for a week, recorded sales may understate demand. Check actual delivery times by warehouse, too. A supplier that reaches Riyadh in five days may need a different allowance for another branch.

A four-week purchasing trial

Choose ten fast-moving items in one warehouse. Record stockout days by item, urgent purchase orders and average stock over a four-week baseline. Review suggestions weekly with your buyer and record why each adjustment was made. After four more weeks, compare the two periods, allowing for seasonality. Did urgent orders fall, and how much extra stock did you carry to achieve that?